Edition 30 - December 2005

Are you crazy?!? Change my operating system?!?…


Management of a two-plant metal fabricator with annual sales around $110 million was struggling with how to fix problems of poor delivery reliability, high inventory levels, poor quality and low morale. To make matters worse, the company had recently become unprofitable. Traditional approaches of working more overtime, increasing quality control efforts, and expediting work to satisfy the most vocal customers were exacerbating the problems rather than providing the relief hoped for. Customers and owners alike were losing patience.

Clearly it was time for a change, but to what wasn't clear. After reviewing the operations in depth the culprit was discovered: the operating system, meaning the way product was planned and produced.

The old operating system was a legacy of a time when competition was virtually non-existent and long lead times were the norm. This "leisurely" pace of manufacturing had allowed machine efficiency to be the primary focus. Customers had been willing to wait in exchange for low prices. Times had changed but the company had not.

New management saw the need to convert the existing operating system to one more responsive to customers. That meant increasing the flexibility with which production and material requirements could be changed, rescheduled, and/or reengineered, based on changes in the customer's orders. To accomplish this, a visual shop floor control system along with a sequenced master scheduling system with provisions for resequencing was to be implemented in both manufacturing facilities. The goal was to create discipline and order that would enable flexibility, reliability, productivity, and inventory management to improve. A corollary objective was to reduce scrap generation as a result of improved handling and less crowding.

The cost to implement the new system had to be considered. The whole process of development, training, and implementation would take four months, plus another two months to refine and seat the sustainability of such a big undertaking. What with training time, some diminished production, some more overtime, and some outside help to facilitate the development of shop floor control processes and I.T. support needed by the master scheduling system, the cost per plant was estimated to be a little under $1.1 million dollars. Included in this was the impact flushing out the work-in-process inventory that had supported a four week manufacturing cycle time if the manufacturing cycle time was reduced.

There were benefits expected as a result of the operating system change. Goals were established to determine the success of the implementation. These included:

1) A 10% improvement in productivity with a stretch goal of 15%, as measured by total labor hours worked per pounds shipped (history of mix and products shipped was very stable.

2) A 25% reduction in the value of Work-in-Process inventory with no increase in raw materials or finished goods. The stretch goal was a 70% reduction.

3) On-time deliveries to customer request date exceeding 90% (current levels were below 35%). The stretch goal was to eliminate lead times all together and give scheduling authority to the customer.

4) A quality measure was developed to reflect doing it right the first time. First pass yields were currently less than 50%. The goal was to achieve first pass yields of 75% with a stretch of 90%.

The ultimate test of the value of this costly overhaul would be the company's return to profitability. However, coming up with the right measure wasn't easy. Profitability as a percentage of sales was important but could be affected by a number of other factors, such as price changes. Plus, inventory reductions wouldn't directly show up on the income statement but had a significant impact on the balance sheet and cash.

An improvement in gross margin was decided as the key measure. Since labor represented 15% of sales, the average labor cost per plant was in excess of $8.4 million annually; a 10% improvement would add $840,000 to the gross profit. In addition, the targeted improvement in first pass yield was calculated to reduce material costs by 2%. Since material equaled 48% of sales, a 2% reduction amounted to an extra $528,000 of gross profit annually. No attempt was made to quantify the value of meeting customer deliveries. Placing a value for having fewer inventories was also problematic. There was value but it didn't translate well to gross margin for people on the shop floor. However, they could relate to faster cycle times. So the performance measure used was manufacturing cycle time, with a goal to eliminate at least one week from the current four weeks. The stretch was to eliminate 3 weeks. It was determined that eliminating a day of manufacturing cycle time would reduce interest expense by $4035 based on the cost of carrying inventory at 10% in annual interest for the cash to fund it. Thus, a one week reduction was worth an additional $28,245 annually. This would be added to the improvements in gross profits for an overall operating return calculation.

Consequently, the determination was that investing $1.1 million dollars at each plant would generate a significant return in a fairly short period of time. In fact, the productivity gain was over 11% within two months of launch and first pass yield increased to 90% within the first few weeks. Equally important, Work-in-Process inventory was reduced significantly when the manufacturing cycle time was reduced from 4 weeks to 1 week immediately upon launch. Actual costs were slightly under $800,000 for each plant. The payback was under seven months.

In summary, what appeared to be an expensive undertaking at first (spending over a million dollars per plant) turned into a huge savings. Traditional methods of quantifying the benefits worked and were able to demonstrate the value of a better alternative. For those of you contemplating your next move, consider the total picture when determining whether it's better to keep doing what you're doing or taking a new approach. Your decision may mean the difference between survival and failure.

November 2005 Newsletter

May 2006 Newsletter



HOME | MISSION | ABOUT SPM | SYNCHRONOUS FLOW ORGANIZATIONS
| SYNCHRONOUS FLOW ASSESSMENT | PRINCIPALS | TYPICAL ENGAGEMENTS |
PREVIOUS ENGAGEMENTS | FAQ'S | PUBLICATIONS | CONTACT US